Officer-in-charge of COnstruction Pearl Harbor Naval ShipYard

MISSION:
The Officer in Charge of Construction, Pearl Harbor Naval Shipyard (OICC PHNSY) delivers Shipyard Infrastructure Optimization Program (SIOP) facilities, utilities, and other supporting infrastructure to optimize Navy Attack Submarine overhaul, repair and modernization.

VISION: 
We exist to deliver SIOP construction projects enabling Fleet warfighter readiness. As an Echelon IV command within the Naval Facilities Engineering Systems Command (NAVFAC), we exercise NAVFAC technical and acquisition authorities and apply engineering, construction and acquisition expertise directly contributing to National Deterrence. DD5 and SIOP repair construction supports the No ka Oi shipyard legacy with increased nuclear ship maintenance.
DRY DOCK 5 CONSTRUCTION PROGRESS UPDATE: AUGUST 2026

August brought continued progress across the P-209 Dry Dock 5 project for the Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY).

The team added a second temporary concrete batch plant onsite to support construction of the dry dock walls. For perspective, Oahu has six permanent concrete batch plants, while P-209 now has two dedicated to this project.

Deep below the water’s surface, crews placed 300 cubic yards of leveling course for the dry dock pump well, which will help remove water from the dock. Crews are now preparing the reinforcing steel for the next underwater concrete slab.

Across the project, crews are also installing utilities, placing underwater concrete, and building the waterfront walls. The team reached an important milestone by driving the final pile for the east wall and completed the concrete foundation for a new electrical substation, while making progress on concrete grade rail beams.

Dry Dock 5 Information


Dragados/Hawaiian Dredging/Orion JV, Honolulu, Hawaii, was awarded a $2,839,880,250 firm-fixed price task order (N62742-23-F-4007) under previously awarded multiple award construction contract for the construction of a concrete dry dock at Pearl Harbor Naval Shipyard.  Work will be performed in Hawaii, and is expected to be completed by September 2027.  This contract is part of the Shipyard Infrastructure Optimization Program (SIOP) which is a holistic plan that integrates all infrastructure and industrial plant equipment investments at the Navy’s four public shipyards to meet nuclear fleet maintenance requirements.  The Naval Facilities Engineering Systems Command, Pacific, Joint Base Pearl Harbor-Hickam, Hawaii, is the contracting activity.

Additional information regarding the project and the Environmental Impact Statement can be found here.